Reliable, rapid drain unblocking…

01227 252361

Canterbury

Our Work Projects

Royal Harbour Academy - February 2026

We cut a trench through the running track and excavated to expose the damaged pipe. This was replaced for new plastic 100mm pipe. A new 24 crate soakaway to take the surface water off the track through a slot drainage was installed to the outside of the track. The site was then fully reinstated including a layer of 100mm tarmac by an outside company. The track was then going to be reinstated by a specialist company. The site was left clean and tidy.

Stone Cross Lees - February 2026

On a CCTV drainage survey at his property it was discovered it had a collapsed line under the edge of the property so we excavated just outside the wall the expose the collapse. Wee then replace this for new 100mm plastic. The site was then fully reinstated and the customer was left happy with the work.

Broadstairs drain unblocking service - January 2026

Blocked drain cleared quickly with full flow restored. Customer left with a clean, fully functioning drainage system.

Burst water main repair - January 2026

Fault located, pipe exposed and repaired, with water supply restored quickly to prevent further damage

Collapsed drain - excavated, repaired and reinstated, March 2025

Excavated and renewed the water main with new ducting and fully reinstated, February 2025

Faulty Gully replace - 2025

Drain excavation - 2025

The drain was excavated and repaired, as you can see when we excavate we carefully lift the blocks and lay them out in order, so when we replace they go back in perfect order, we take great pride in our work and hope you agree. Any blockage, any repair, we are here for you.

Water Main Repair May 2023

We were called to a lady who had been told by Southern Water she had a water leak somewhere on her main between her meter and her connection into her house. We traced the line of the water main and excavated onto it. We then found there were multiple leaks on her old steel pipe.  

We dug out the whole length of 20 meters and installed a new MDPE pipe at a depth of 750mm with a sleeve over it to protect from freezing. We then surrounded with shingle to protect the pipe and backfilled. The whole site was then fully reinstated to its original condition including replacing the block paving.

This was done as an emergency as the customer only had so much time before Southern Water started charging her for the water from the leak. The customer was left happy with the work carried out.

Channel Drainage Installation March 2023

We installed 3 meters of channel drainage where there was flooding before, a new downpipe from and existing line into a new gully and a new 34mm pipe from a basin into and existing gully. The job was fully reinstated, and the customer was very happy with the work carried out.

Care Home Drainage Installation March 2023

This job was a care home in Westgate. The whole homes drains were backing up and Simon had realised there was a hidden manhole that was blocked. He located the manhole under some concrete and manged to excavate and reveal it. When he lifted the lid he was met with an absolute Tsunami of foul waste that burst out the top of the manhole and flushed down the street. He has since dug out the manhole lid and raised it to ground level so if there are future blockages they can be cleared a lot easier.

Ramsgate excavation March 2023

We were instructed to carry out and excavation on a collapsed line, 3 meters deep. Using our camera and scanning equipment we located the exact spot of the collapse and excavated onto the pipe. When we dug down and revealed the collapse we found the pipe had also collapsed further downstream, so we had to excavate onto that pipe too. The job took 7 days in total. The collapsed lines were replaced and the drains are running clear now. Job was fully reinstated to its original condition.